Bexar Release schedule
- Status: Confirmed
Chief Architect: Rick Clark (dendrobates)
Release Manager: Thierry Carrez (ttx)
Week (Thursday) |
Freezes |
Milestones |
November 2010 |
||
November 11th |
|
|
November 18th |
SpecsSubmissionDeadline (Nov 18) |
|
November 25th |
|
|
December 2010 |
||
December 2nd |
|
|
December 9th |
|
|
December 16th |
|
|
December 23rd |
|
|
December 30th |
|
|
January 2011 |
||
January 6th |
BranchMergeProposalFreeze (Jan 6) |
|
January 13th |
FeatureFreeze (Jan 13) |
|
January 20th |
|
|
January 27th |
GammaFreeze (Jan 27) |
Gamma (Jan 28) |
February 2011 |
||
February 3rd |
RCFreeze (Feb 1) |
RC (Feb 2), Release (Feb 3) |